Magnum One Progress
Dated: 26/02/2024
Possession Soon
Dated: 28/08/2022
Structure Completed
HVAC
Piping work in progress, Cooling tower installation work in progress, Basement ventilation work in progress
Plumbing & Fire Fighting
Plumbing & fire fighting work in progress
Painting work of basement in progress
Electrical Works
Conducting work in progress in the basement
Elevator delivered at site & installation in progress
External Facade work in progress (20% complete)
Others
External development work – rain water harvesting, storm water drainage, main holes & RCC of boundary walls etc. in progress LT panel panels delivered & installed at site
Façade Cleaning system awarded
DG tender floated
Chillers tender floated
STP Tenders floated
Dated: 25/02/2022
All floors completed (14 floors)
HVAC
Piping work started
Plumbing & Fire Fighting
Plumbing & fire fighting work in progress
Painting work of basement in progress
Electrical Works
Conducting work in progress in basement
Elevator work awarded to Toshiba elevators
External Facade work awarded
03/09/2021
13th floor completed
14th floor work in progress
Plumbing & fire fighting work in progress
Painting work of basement in progress
23/06/2021
11th floor completed
12th floor work in progress
Plumbing & fire fighting work in progress
Painting work of basement in progress
12/04/2021
9th floor completed
10th floor work in progress
Plumbing & fire fighting work in progress
Painting work of basement in progress
1/12/2020
7th floor completed
8th floor work in progress
Tender Floated
18/08/2020
Ground & First floor completed
2nd Floor work in progress
07/02/2020
Ground floor slab under process.
01/05/2018
Basement 3 – Complete
Basement 2 – Casted
Basement 1 – Partly Casted
01/01/2018
Basement 3 Casted
Basement 2 Casted
Basement 1 in Progress