M1 Trade Tower
Structure Completed
HVAC
Piping work in progress, Cooling tower installation work in progress, Basement ventilation work in progress
Plumbing & Fire Fighting
Plumbing & fire fighting work in progress
Painting work of basement in progress
Electrical Works
Conducting work in progress in the basement
Elevator delivered at site & installation in progress
External Facade work in progress (20% complete)
Others
External development work – rain water harvesting, storm water drainage, main holes & RCC of boundary walls etc. in progress
LT panel panels delivered & installed at site
Façade Cleaning system awarded
DG tender floated
Chillers tender floated
STP Tenders floated
All floors completed (14 floors)
HVAC
Piping work started
Plumbing & Fire Fighting
Plumbing & fire fighting work in progress
Painting work of basement in progress
Electrical Works
Conducting work in progress in basement
Elevator work awarded to Toshiba elevators
External Facade work awarded
13th floor completed
14th floor work in progress
Plumbing & fire fighting work in progress
Painting work of basement in progress
11th floor completed
12th floor work in progress
Plumbing & fire fighting work in progress
Painting work of basement in progress
9th floor completed
10th floor work in progress
Plumbing & fire fighting work in progress
Painting work of basement in progress
7th floor completed
8th floor work in progress
Tender Floated
Ground & First floor completed
2nd Floor work in progress
Ground floor slab under process.
Basement 3 – Complete
Basement 2 – Casted
Basement 1 – Partly Casted
Basement 3 Casted
Basement 2 Casted
Basement 1 in Progress