M1 Trade Tower

Dated: 28/08/2022

Structure Completed

HVAC
Piping work in progress, Cooling tower installation work in progress, Basement ventilation work in progress

Plumbing & Fire Fighting
Plumbing & fire fighting work in progress
Painting work of basement in progress

Electrical Works
Conducting work in progress in the basement
Elevator delivered at site & installation in progress
External Facade work in progress (20% complete)

Others
External development work – rain water harvesting, storm water drainage, main holes & RCC of boundary walls etc. in progress LT panel panels delivered & installed at site
Façade Cleaning system awarded
DG tender floated
Chillers tender floated
STP Tenders floated

Dated: 25/02/2022

All floors completed (14 floors)

HVAC
Piping work started

Plumbing & Fire Fighting
Plumbing & fire fighting work in progress
Painting work of basement in progress

Electrical Works
Conducting work in progress in basement
Elevator work awarded to Toshiba elevators

External Facade work awarded

Dated: 03/09/2021

13th floor completed
14th floor work in progress
Plumbing & fire fighting work in progress
Painting work of basement in progress

Dated: 23/06/2021

11th floor completed
12th floor work in progress
Plumbing & fire fighting work in progress
Painting work of basement in progress

Dated: 12/04/2021

9th floor completed
10th floor work in progress
Plumbing & fire fighting work in progress
Painting work of basement in progress

Dated: 01/12/2020

7th floor completed
8th floor work in progress
Tender Floated

Dated: 18/08/2020

Ground & First floor completed
2nd Floor work in progress

Dated: 07/02/2020

Ground floor slab under process.

Dated: 01/05/2018

Basement 3 – Complete
Basement 2 – Casted
Basement 1 – Partly Casted

Dated: 01/01/2018

Basement 3 Casted
Basement 2 Casted
Basement 1 in Progress