Magnum City Centre

 
Dated: 15/06/2022

Structure Completed

Plumbing & Fire Fighting
Basement 1,2 & 3 completed
Ground - 4th floor completed,
Fire pumps installation work in progress
Fire NOC Applied

HVAC
Ventilation work of basement 1,2,3 completed
Ventilation work of vertical risers completed
Ventilation fans installation work completed
Floor/basement fresh air work completed.

Electrical Works
Electrical conducting completed
Cable tray laying completed
Elevator work installation work in progress
Basement wiring in conduit done

External Facade
External Facade Work Completed

Power Back Up Installation
DG work in progress
Solar work in progress