Magnum City Centre
Dated: 15/06/2022
Structure Completed
Plumbing & Fire Fighting
Basement 1,2 & 3 completed
Ground - 4th floor completed,
Fire pumps installation work in progress
Fire NOC Applied
HVAC
Ventilation work of basement 1,2,3 completed
Ventilation work of vertical risers completed
Ventilation fans installation work completed
Floor/basement fresh air work completed.
Electrical Works
Electrical conducting completed
Cable tray laying completed
Elevator work installation work in progress
Basement wiring in conduit done
External Facade
External Facade Work Completed
Power Back Up Installation
DG work in progress
Solar work in progress