Magnum Tower 1 & 2

Dated: 30/01/2019

Magnum Tower 1
OC Received

Dated: 30/01/2019

Magnum Tower 2
OC Received

Dated: 01/05/2018

Magnum Tower 1
OC Applied

Dated: 01/05/2018

Magnum Tower 2
Ready for Fitouts
OC Applied

Dated: 01/01/2018

Magnum Tower 1
Ready for fitouts

Dated: 01/01/2018

Magnum Tower 2
Nearing completion
Ready for fitouts by February 2018

Dated: 29/04/2017

Magnum Tower 1
Facade complete
Elevators installed
HVAC work nearing completion
Chillers placed at site
Reception/Entrance lobby work in progress
Finishing work in progress

Dated: 29/04/2017

Magnum Tower 2
Facade work started
Fire fighting work nearing completion
HVAC & lift work in progress

Dated: 04/03/2017

Magnum Tower 1
Facade & HVAC work nearing completion
Reception/Entrance Lobby work started
Boundary wall completed
Finishing work in progress

Dated: 04/03/2017

Magnum Tower 2
Fire Fighting & Plumbing work in progress
HVAC & lift work in progress

Dated: 02/01/2017

Magnum Tower 1
Facade nearing completion
Lift installation & other services in progress
External development work started

Dated: 02/01/2017

Magnum Tower 2
Structure Complete
Internal services work in progress
External development work started

Dated: 22/09/2016

Magnum Tower 1
Facade Work in Progress

Dated: 22/09/2016

Magnum Tower 2
Structure Complete

Dated: 31/05/2016

Magnum Tower 1
Facade Work in Progress

Dated: 31/05/2016

Magnum Tower 2
Seventh Floor Slab Casted

Dated: 04/10/2015

Magnum Tower 1
Internal Services work in progress

Dated: 04/10/2015

Magnum Tower 2
Ground Floor casting completed

Dated: 10/09/2015

Magnum Tower 2
Casting of all three basements completed

Dated: 18/08/2015

Magnum Tower I
Structure Completed

Dated: 25/06/2015

Magnum Tower 2
Basement 2 completed

Dated: 25/06/2015

Magnum Tower I
Tenth Floor casting completed

Dated: 15/04/2015

Magnum Tower II Launched
at Sector 58, Golf Course Extension Road

Dated: 25/03/2015

Magnum Tower I
8th Floor Casting Completed

Dated: 05/02/2015

Magnum Tower I
Fifth Floor Casting Completed

Dated: 25/12/2014

Magnum Tower I
Casting of Third Floor Slab Completed

Dated: 15/11/2014

Magnum Tower I
Casting of First Floor Slab Completed

Dated: 15/10/2014

Magnum Tower I
Casting of Upper Ground Floor Slab Completed.

Dated: 01/09/2014

Magnum Tower I
Casting of Ground Floor slab completed.

Dated: 01/08/2014

Magnum Tower I
All three basement floor slabs completed

Dated: 25/06/2014

Magnum Tower I
Casting of first basement floor slab completed.

Dated: 01/05/2014

Magnum Tower I
Magnum Tower third basement roof slab completed – second roof slab in progress.

Dated: 16/11/2013

Magnum Tower I
Magnum Tower excavation completed – Construction in full swing