9911368744

Magnum Global Park

Dated: 22/06/2023


Facade work 80% complete
External hard scaping & internal roads 80% done.
Landscaping work started
Chiller’s installed
DG installed
IT panel installed
Firefighting & pump room installation complete
3 no. Of lift operational on slow speed
Lift area facade 50% complete

Dated: 28/08/2022

Structure Completed

Plumbing & Fire Fighting
Basement 1,2 & 3 completed MLCP 1, 2,3,4 & 5 completed,
Ground – 20th floor completed,
21st – 22nd floor in progress,
Fire pump room installation work completed

HVAC
Ducting work of basement 1,2,3 in progress,
Ventilation work of vertical risers in progress,
Ventilation fans installation work in progress

Electrical Works
Electrical conducting in progress Cable tray laying in progress,
Basement wiring in conduit in progress

External Facade
Facade Work in progress (Glass and Aluminium)

Block 1
Raft foundation 90% completed
2nd basement roof slap 50% completed
1st basement retaining wall in progress

Other
Earth filling & landscape area in progress
External development work – rain water harvesting, storm water drainage, main holes & RCC of boundary walls etc. in progress Elevator delivered at site & installation in progress.
LT panel panels delivered & installed at site
DG work in progress
Chillers awarded
Façade Cleaning system awarded
STP Tender floated

Dated: 26/07/2022

Structure Completed

Plumbing & Fire Fighting
Basement 1,2 & 3 completed
MLCP 1, 2,3,4 & 5 completed
Ground – 20th floor completed, 21st – 22nd floor in progress
Fire pump room installation work completed

HVAC
Ducting work of basement 1,2,3 in progress
Ventilation work of vertical risers in progress
Ventilation fans installation work in progress

Electrical Works
Electrical conducting in progress
Cable tray laying in progress
Elevator work guide rails installation in progress
Basement wiring in conduit in progress

External Facade
Facade Work in progress ( Glass and Aluminium )

Other
Block 1 raft foundation in progress
Earth filling & landscape area in progress
External development work – rain water harvesting, storm water drainage, main holes & RCC of boundary walls etc. in progress
LT panel work awarded
DG work awarded


Dated: 25/02/2022

All floors Completed (22 floors)

Plumbing & Fire Fighting
Basement 1,2 & 3 completed
MLCP 1, 2,3,4 & 5 completed
Ground to 17th floor completed, 18th floor in progress.
Fire pumps installation work in progress

HVAC
Ducting work of basement 1,2,3 in progress
Ventilation work of vertical risers in progress
Ventilation fans installation work in progress

Electrical Works
EElectrical conducting in progress
Cable tray laying in progress
Elevator work awarded to Toshiba Elevators
Basement wiring in conduit in progress

External Facade
External Facade Work Awarded
Contractor mobilized at site

Dated: 03/09/2021

18th Floor Completed
19th floor work in progress

Plumbing & Fire Fighting
Basement 1,2 & 3 completed
MLCP 1, 2,3,4 & 5 completed
Ground to 11th floor completed 12th & 13th floor in progress.

HVAC
Ducting work of basement 1,2,3 in progress

Electrical Works
Electrical conducting in progress
Cable tray laying in progress
Elevator tenders floated

Dated: 01/07/2021

16th Floor Completed
17th floor work in progress

Plumbing & Fire Fighting
Basement 1,2 & 3 completed
MLCP 1, 2,3,4 & 5 completed
Ground to 10th floor completed 11th & 12th floor in progress.

HVAC
Ducting work of basement 1,2,3 in progress

Electrical Works
Electrical conducting in progress
Cable tray laying in progress
Elevator tenders floated

Dated: 12/04/2021

14th Floor Completed
15th floor work in progress

Plumbing & Fire Fighting
Basement 1,2 & 3 completed
MLCP 1, 2,3,4 & 5 completed
Ground floor to 7th floor completed 8th, 9th floor in progress.

HVAC
Ducting work of basement 1,2,3 in progress

Electrical Works
Electrical conducting in progress

Dated: 01/12/2020

10th Floor Completed (Including 1-5 MLCP)
11th floor work in progress

Plumbing & Fire Fighting
Basement 1, 2 & 3 completed
MLCP 1, 2,3 & 4 Completed
Ground floor & MLCP 5th in progress

HVAC
Ducting work of basement 2 in progress

Electrical Works
Electrical conducting in progress

Landscape & Road work
Earth filling of landscape area in progress

Dated: 18/08/2020

Ground Floor to 7th Floor Completed (Including 1-5 MLCP)
8th & 9th floor work in progress

Fire Fighting
Basement 2 & 3 work completed
MLCP 1 & 2 Completed
Basement 1 & MLCP 3 work in progress
HVAC & Electrical work awarded to Blue Star Limited
Mobilization in progress

Dated: 30/01/2020

Ground, 1st & 2nd floor complete
3rd MLCP - 100% casted
4th MLCP - 50% casted.
5th MLCP work started
Basement 2 & 3 fire fighting work in progress
HVAC & electrical tenders floated

Dated: 23/09/2019

All 3 basements casted along with ground Floor Casted
First Floor (MLCP 1 80% Casted)
Second Floor (MLCP 2 70% Casted)
Third Floor (MLCP 3 shutting work in progress)
Plumbing & Fire fighting work Awarded

Dated: 19/04/2019

3rd & 2nd basement casted
1st basement 50% casted, balance area under progress
Ground floor shuttering started
IGBC - pre - certified gold rating obtained

Dated: 01/04/2019

3rd & 2nd basement casted
1st basement casting in progress