Magnum Global Park
All floors Completed (22 floors)
Plumbing & Fire Fighting
Basement 1,2 & 3 completed
MLCP 1, 2,3,4 & 5 completed
Ground to 17th floor completed, 18th floor in progress.
Fire pumps installation work in progress
HVAC
Ducting work of basement 1,2,3 in progress
Ventilation work of vertical risers in progress
Ventilation fans installation work in progress
Electrical Works
Electrical conducting in progress
Cable tray laying in progress
Elevator work awarded to Toshiba Elevators
Basement wiring in conduit in progress
External Facade
External Facade Work Awarded
Contractor mobilized at site
18th Floor Completed
19th floor work in progress
Plumbing & Fire Fighting
Basement 1,2 & 3 completed
MLCP 1, 2,3,4 & 5 completed
Ground to 11th floor completed 12th & 13th floor in progress.
HVAC
Ducting work of basement 1,2,3 in progress
Electrical Works
Electrical conducting in progress
Cable tray laying in progress
Elevator tenders floated
16th Floor Completed
17th floor work in progress
Plumbing & Fire Fighting
Basement 1,2 & 3 completed
MLCP 1, 2,3,4 & 5 completed
Ground to 10th floor completed 11th & 12th floor in progress.
HVAC
Ducting work of basement 1,2,3 in progress
Electrical Works
Electrical conducting in progress
Cable tray laying in progress
Elevator tenders floated
14th Floor Completed
15th floor work in progress
Plumbing & Fire Fighting
Basement 1,2 & 3 completed
MLCP 1, 2,3,4 & 5 completed
Ground floor to 7th floor completed 8th, 9th floor in progress.
HVAC
Ducting work of basement 1,2,3 in progress
Electrical Works
Electrical conducting in progress
10th Floor Completed (Including 1-5 MLCP)
11th floor work in progress
Plumbing & Fire Fighting
Basement 1, 2 & 3 completed
MLCP 1, 2,3 & 4 Completed
Ground floor & MLCP 5th in progress
HVAC
Ducting work of basement 2 in progress
Electrical Works
Electrical conducting in progress
Landscape & Road work
Earth filling of landscape area in progress
Ground Floor to 7th Floor Completed (Including 1-5 MLCP)
8th & 9th floor work in progress
Fire Fighting
Basement 2 & 3 work completed
MLCP 1 & 2 Completed
Basement 1 & MLCP 3 work in progress
HVAC & Electrical work awarded to Blue Star Limited
Mobilization in progress
Ground, 1st & 2nd floor complete
3rd MLCP - 100% casted
4th MLCP - 50% casted.
5th MLCP work started
Basement 2 & 3 fire fighting work in progress
HVAC & electrical tenders floated
All 3 basements casted along with ground Floor Casted
First Floor (MLCP 1 80% Casted)
Second Floor (MLCP 2 70% Casted)
Third Floor (MLCP 3 shutting work in progress)
Plumbing & Fire fighting work Awarded
3rd & 2nd basement casted
1st basement 50% casted, balance area under progress
Ground floor shuttering started
IGBC - pre - certified gold rating obtained
3rd & 2nd basement casted
1st basement casting in progress